Iraq's Mosul Dam In Critical Need Of Repair

Iraq

Iraq's Mosul Dam In Critical Need Of Repair

Iraq's Mosul Dam In Critical Need Of Repair
  • Download
  • <iframe src="https://www.npr.org/player/embed/469299839/469299840" width="100%" height="290" frameborder="0" scrolling="no" title="NPR embedded audio player">
  • Transcript

Engineers warn that the Mosul dam in Iraq could collapse at any time, threatening 1.5 million people. Needed repairs on the poorly built structure haven't been carried out since ISIS held it.

LOURDES GARCIA-NAVARRO, HOST:

The Mosul dam in Iraq is in danger of collapsing. If it fails, it could cause massive loss of life in the city of Mosul and beyond.

NADHIR AL-ANSARI: The discharge of water will be about 500,000 cubic meters per second. And the height of the wave of water will be about 28 meters. It will flood about 75 percent of the city. And then the wave will progress down and fill (unintelligible).

GARCIA-NAVARRO: That's Nadhir Al-Ansari. He's a professor of civil engineering at Lulea University of Technology in Sweden. Thirty years ago, he compiled the first report on the structural problems there. The dam was built, he says, in the wrong place. After he filed that report, a process of grouting began. That's to stop seepage of water that had begun to leak through the dam. Large teams of workers had to shore it up 24 hours a day in order to keep it operational. The dam survived even a bombing. But then came ISIS.

AL-ANSARI: In 2014, ISIS occupied the dam. And when they occupied the dam, all the engineers and workers, they run away and machines were destroyed. And even when they recaptured the dam, nobody has done any grouting.

GARCIA-NAVARRO: Nadhir Al-Ansari says the government needs to put an evacuation plan in place for people who live in areas that would be flooded if the dam were breached. But that hasn't happened. This past week, authorities in Baghdad hired an Italian firm to start repairs again. But it's not a permanent solution. And the renovation project won't start right away. And as the snows melt this month, more water is flowing into the reservoir above the dam. It's left Nadhir Al-Ansari very, very concerned.

AL-ANSARI: Really, I am very frightened. They don't have that much material and the machinery are not enough to do the required quantities of grouting. So we are very worried that if a flood comes next month, that might destroy the dam.

GARCIA-NAVARRO: That, he says, would be catastrophic. Hundreds of thousands of people could drown.

Copyright © 2016 NPR. All rights reserved. Visit our website terms of use and permissions pages at www.npr.org for further information.

NPR transcripts are created on a rush deadline by Verb8tm, Inc., an NPR contractor, and produced using a proprietary transcription process developed with NPR. This text may not be in its final form and may be updated or revised in the future. Accuracy and availability may vary. The authoritative record of NPR’s programming is the audio record.

Comments

 

Please keep your community civil. All comments must follow the NPR.org Community rules and terms of use, and will be moderated prior to posting. NPR reserves the right to use the comments we receive, in whole or in part, and to use the commenter's name and location, in any medium. See also the Terms of Use, Privacy Policy and Community FAQ.